City of Boston Delegation v. FERC

by
Petitioners challenged FERC's approval of an application from Algonquin to undertake an upgrade to its natural gas pipeline system. The DC Circuit dismissed the Delegation's petition for review for lack of jurisdiction because the Delegation failed to establish that it had standing to seek review of the Commission's decision where its individual members did not suffer an injury in fact from the pipeline project. The court held that the remaining petitioners adequately demonstrated standing and thus reached the merits of their petitions.On the merits, the court held that the Commission did not act arbitrarily and capriciously in declining to consider Algonquin's three projects in a single environmental impact statement. The court explained that, for purposes of the AIM Project, the Commission adequately considered the cumulative impacts of the other two projects based on the information then available to the agency. The court also held that the Commission gave adequate consideration to the cumulative environmental impacts of the three upgrade projects. View "City of Boston Delegation v. FERC" on Justia Law