Justia U.S. D.C. Circuit Court of Appeals Opinion Summaries

Articles Posted in Energy, Oil & Gas Law
by
The Alaska LNG Project sought authorization from the Department of Energy to export up to twenty million metric tons of liquefied natural gas (LNG) per year for thirty years. The Department initially authorized the Project to export LNG to free-trade countries in 2014 and later to non-free trade countries in 2015, subject to environmental review. In 2023, the Department issued a final order approving the Project’s export application, concluding that the approval was consistent with the public interest despite uncertainties regarding environmental impacts.The Federal Energy Regulatory Commission (FERC) had previously authorized the construction and operation of the Project’s facilities, including an 800-mile pipeline and associated infrastructure, after preparing an extensive environmental impact statement. The U.S. Court of Appeals for the District of Columbia Circuit upheld FERC’s compliance with the National Environmental Policy Act (NEPA) in Center for Biological Diversity v. FERC. The Department of Energy adopted FERC’s impact statement and issued its own supplemental environmental impact statement in response to Executive Order 13990.The United States Court of Appeals for the District of Columbia Circuit reviewed the Department of Energy’s final order. The court found that the Department had properly adopted FERC’s environmental impact statement and complied with NEPA. The court also upheld the Department’s finding of substantial uncertainty regarding the magnitude of environmental impacts, particularly greenhouse gas emissions and climate impacts, associated with the Project’s exports. The court concluded that the impacts of downstream emissions in foreign countries were not reasonably foreseeable and that the Department’s analysis was supported by substantial evidence.The court denied the petitions for review, affirming the Department of Energy’s authorization for the Alaska LNG Project to export LNG. View "Sierra Club v. DOE" on Justia Law

by
Entergy companies petitioned for review of three orders by the Federal Energy Regulatory Commission (FERC). FERC had rejected tariff changes proposed by Midcontinent Independent System Operator (MISO), arguing that the new tariff would grant Entergy excessive market power. Entergy contended that FERC’s decisions were arbitrary and capricious.The case was reviewed by the United States Court of Appeals for the District of Columbia Circuit. Entergy’s opening brief did not address the issue of standing, which is a jurisdictional prerequisite. This omission violated Circuit Rule 28(a)(7), which requires petitioners to set forth the basis for their claim of standing in their opening brief. As a result, Entergy forfeited any arguments in support of standing.The D.C. Circuit Court dismissed the petitions for review, stating that Entergy lacked standing. The court emphasized that Entergy’s failure to discuss standing in its opening brief constituted a forfeiture of the argument. Even if the court were to consider the standing arguments Entergy later advanced, the company did not demonstrate the necessary concrete, imminent, and redressable injury. The court concluded that dismissal was the appropriate consequence for Entergy’s failure to establish standing. View "Entergy Arkansas, LLC v. FERC" on Justia Law

by
Driftwood Pipeline LLC sought approval from the Federal Energy Regulatory Commission (FERC) to build two new natural gas pipelines in southwestern Louisiana. FERC granted the approval, concluding that the project would serve a market need and that its benefits outweighed its adverse environmental impacts. Healthy Gulf and Sierra Club challenged this decision, arguing that FERC failed to comply with the National Environmental Policy Act (NEPA) and the Natural Gas Act.The Federal Energy Regulatory Commission (FERC) issued a Section 7 certificate to Driftwood Pipeline LLC, determining that the project was required by public convenience and necessity. FERC also published an environmental impact statement, concluding that the project would have some adverse environmental impacts but none that were significant. Healthy Gulf and Sierra Club requested a rehearing, which was deemed denied when FERC did not act on it. They then petitioned for review, raising challenges under NEPA and the Natural Gas Act.The United States Court of Appeals for the District of Columbia Circuit reviewed the case. The court held that FERC adequately considered the environmental effects of the project, including its impact on greenhouse gas emissions, and found that FERC's refusal to characterize the significance of these emissions was reasonable. The court also found that FERC's determination of market need was supported by substantial evidence, including precedent agreements and an independent market study. The court concluded that FERC had properly balanced the project's benefits against its adverse effects and denied the petition for review. View "Healthy Gulf v. FERC" on Justia Law

by
Hecate Energy, LLC, a developer and operator of renewable power facilities, petitioned for review of two orders by the Federal Energy Regulatory Commission (FERC). These orders approved reforms proposed by PJM Interconnection, LLC, a regional transmission grid operator, to the criteria used for processing requests to connect new electricity sources to the grid. Hecate challenged the approval of a specific aspect of these reforms: the expedited processing of interconnection requests projected to incur upgrade costs of $5 million or less. Hecate argued that this cap was arbitrary and unduly discriminatory.The Federal Energy Regulatory Commission (FERC) approved PJM's proposed reforms, including the $5 million cap, and denied Hecate's request for rehearing. FERC justified the cap by stating that projects with upgrade costs of $5 million or less were simpler and quicker to process. Hecate then petitioned the United States Court of Appeals for the District of Columbia Circuit for review, arguing that the cap was not supported by substantial evidence and that FERC failed to consider alternative eligibility rules.The United States Court of Appeals for the District of Columbia Circuit dismissed Hecate's petitions for lack of standing. The court held that Hecate's injury was not redressable because vacating FERC's approval of the $5 million cap would not likely lead to the expediting of Hecate's project. The court reasoned that PJM had multiple options to address the alleged defect without necessarily including Hecate's project in the expedited process. Therefore, Hecate failed to demonstrate that its injury would be alleviated by the court's intervention. View "Hecate Energy LLC v. FERC" on Justia Law

by
Aclara Meters LLC owned the license for the Somersworth Hydroelectric Project on the Salmon Falls River between New Hampshire and Maine from 2016 to 2023. In 2019, Aclara sought to surrender its license to the Federal Energy Regulatory Commission (FERC). After conducting an environmental assessment, FERC authorized the surrender in 2023. American Whitewater, a conservation organization, requested a rehearing, arguing that two dams from the Project should be removed as a condition of surrender. FERC denied the request, leading Whitewater to petition the United States Court of Appeals for the District of Columbia Circuit for relief, claiming that FERC acted arbitrarily and capriciously under the Federal Power Act (FPA) and the National Environmental Policy Act (NEPA).The Commission's environmental assessment concluded that approving the surrender as proposed would not significantly affect the environment, thus an Environmental Impact Statement (EIS) was unnecessary. FERC found that removing the dams was unfeasible due to the local municipalities' reliance on the reservoir for water supply and other needs. The Commission also determined that the benefits of keeping the dams outweighed the environmental and recreational benefits of their removal. FERC's decision was based on the public interest, considering the water supply, firefighting needs, and potential impacts on local infrastructure.The United States Court of Appeals for the District of Columbia Circuit reviewed the case and denied Whitewater's petition for review. The court held that FERC's analysis was neither arbitrary nor capricious. The Commission reasonably determined that dam removal was unfeasible and appropriately assessed the public interest. The court found that FERC's decision to approve the license surrender without dam removal was supported by substantial evidence and consistent with its policies and precedents. View "American Whitewater v. FERC" on Justia Law

by
Petitioners sought review of the Federal Energy Regulatory Commission's (FERC) grant of an abandonment incentive to ITC Midwest, LLC (ITC). This incentive allows ITC to recover 100% of its prudently incurred costs if a planned transmission project is abandoned for reasons beyond its control. Petitioners, a group of organizations whose members purchase electricity, argued that ITC's ownership of the project was uncertain due to ongoing litigation challenging the Iowa Right of First Refusal statute.The Federal Energy Regulatory Commission approved ITC's request for the abandonment incentive, finding that the project met the necessary criteria, including enhancing reliability and reducing congestion. Petitioners filed a protest, which FERC rejected, stating that regulatory or litigation uncertainty does not preclude granting an abandonment incentive. Petitioners then sought rehearing, which FERC also denied, reiterating that the approval was consistent with its precedent.The United States Court of Appeals for the District of Columbia Circuit reviewed the case. The court determined that petitioners lacked Article III standing because they failed to show imminent injury from FERC's orders. The court noted that petitioners' claims of potential future higher rates were speculative and not concrete or imminent. The court also found that petitioners' interest in the proper application of the law and potential collateral estoppel effects did not constitute a cognizable injury. Consequently, the court dismissed the petition for lack of jurisdiction. View "Industrial Energy Consumers of America v. FERC" on Justia Law

by
The State of Indiana approved a plan to retire a coal-fired facility and replace it with wind and solar energy sources, supplemented by two new natural gas turbines to ensure grid reliability. The Federal Energy Regulatory Commission (FERC) approved a natural gas pipeline to serve these turbines. The Citizens Action Coalition of Indiana challenged FERC’s approval, arguing that FERC’s environmental analysis was unreasonable and inconsistent with the National Environmental Policy Act (NEPA) and the Natural Gas Act (NGA). The core claim was that FERC should have analyzed non-gas alternatives before approving the pipeline.The Indiana Utility Regulatory Commission initially denied CenterPoint Energy’s proposal for an 850-megawatt natural gas unit due to inadequate consideration of alternatives. CenterPoint then modified its plan to include wind generation and applied to build two smaller gas-fired turbines, which the Indiana Commission approved. CenterPoint contracted with Texas Gas Transmission for a 24-mile pipeline to supply natural gas to the new units. Citizens Action intervened in the FERC proceeding, raising environmental concerns. FERC prepared an environmental impact statement and approved the pipeline. Citizens Action’s request for rehearing was denied by operation of law, leading to the current petition for review.The United States Court of Appeals for the District of Columbia Circuit reviewed the case. The court held that FERC acted lawfully and reasonably in its environmental analysis and public convenience and necessity determination. FERC was not required to consider non-gas alternatives outside its jurisdiction and properly identified the project’s purpose as supporting CenterPoint’s new natural gas units. The court also found that FERC’s use of emissions percentages and the absence of a significance label were reasonable and consistent with NEPA. The petition for review was denied. View "Citizens Action Coalition of Indiana, Inc. v. FERC" on Justia Law

by
Stingray Pipeline Company LLC operates a pipeline system under the jurisdiction of the Federal Energy Regulatory Commission (FERC). Due to declining throughput and financial losses, Stingray sought FERC's permission to abandon part of its pipeline network by selling it to a non-jurisdictional entity. However, a hurricane damaged a segment of the pipeline, Segment 3394, which has remained out of service since 2020. FERC granted the abandonment request but imposed a condition that Stingray must either restore Segment 3394 to service or reach an agreement with the affected shipper, ERT.The Federal Energy Regulatory Commission largely granted Stingray's application to abandon the pipeline but imposed the condition regarding Segment 3394. Stingray challenged this condition as unreasonable and unsupported by the record. FERC reaffirmed its order, leading Stingray to petition the United States Court of Appeals for the District of Columbia Circuit for review.The United States Court of Appeals for the District of Columbia Circuit reviewed the case and denied the Petition for Review. The court held that FERC's decision to impose the condition was not arbitrary and capricious. The court found that Stingray had not met its burden to show that unconditional abandonment was consistent with the public convenience and necessity. The court emphasized that Stingray had repeatedly assured FERC that it would restore Segment 3394 to service but failed to provide sufficient evidence to justify abandoning the segment without restoring service or reaching an agreement with ERT. The court also rejected Stingray's arguments that the condition exceeded FERC's regulatory authority. View "Stingray Pipeline Company, L.L.C. v. FERC" on Justia Law

by
NextEra Energy Resources, LLC and NextEra Energy Seabrook, LLC (collectively, "Seabrook") own a nuclear power plant in Seabrook, New Hampshire. Avangrid, Inc. and NECEC Transmission LLC (collectively, "Avangrid") sought to connect their New England Clean Energy Connect (NECEC) project to the regional transmission grid. The connection required Seabrook to upgrade its circuit breaker to handle the increased power flow. Seabrook and Avangrid agreed on the necessity of the upgrade and that Avangrid would cover the direct costs, but they disagreed on whether Seabrook should be compensated for indirect costs and whether Seabrook was obligated to upgrade the breaker without full compensation.The Federal Energy Regulatory Commission (FERC) ruled that Seabrook must upgrade the circuit breaker under the Large Generator Interconnection Agreement (LGIA) and that Avangrid was not required to reimburse Seabrook for indirect costs such as legal expenses and lost profits. Seabrook petitioned for review, arguing that FERC lacked statutory authority to require the upgrade and that the LGIA did not obligate them to upgrade the breaker without full compensation.The United States Court of Appeals for the District of Columbia Circuit reviewed the case. The court held that FERC had statutory authority to require the upgrade because it directly affected the transmission of electricity in interstate commerce. The court also found that FERC correctly interpreted the LGIA to require Seabrook to maintain an adequate circuit breaker in light of changing grid conditions, including the interconnection of new generators like Avangrid. Additionally, the court upheld FERC's decision to deny compensation for indirect costs, reasoning that the tariff did not clearly and specifically cover such costs and that FERC's precedent generally did not allow for recovery of opportunity costs during interconnection outages.The court denied Seabrook's petitions for review, affirming FERC's orders. View "NextEra Energy Resources, LLC v. FERC" on Justia Law

by
Holtec International applied to the Nuclear Regulatory Commission (NRC) for a license to construct and operate a spent nuclear fuel storage facility in New Mexico. The NRC denied multiple requests for intervention and a hearing from various petitioners, including Beyond Nuclear, Sierra Club, and Fasken Land and Minerals. These petitioners argued that the NRC acted unreasonably and contrary to law in denying their requests.The Atomic Safety and Licensing Board (Board) found the petitioners' contentions inadmissible and denied their petitions to intervene. The NRC affirmed the Board’s decisions. Beyond Nuclear, Environmental Petitioners (including Sierra Club), and Fasken each petitioned for review of the orders denying intervention. The case was held in abeyance until the NRC issued Holtec a license, after which the case was removed from abeyance for review by the United States Court of Appeals for the District of Columbia Circuit.The United States Court of Appeals for the District of Columbia Circuit reviewed the petitions and found that the NRC reasonably declined to admit the petitioners' factual contentions and complied with statutory and regulatory requirements. The court held that Beyond Nuclear did not raise a genuine dispute of law or fact regarding the NRC’s authority to consider Holtec’s application. The court also found that Environmental Petitioners failed to demonstrate any genuine disputes of material fact or law in their contentions related to statutory authority, alleged misrepresentations by Holtec, and compliance with the National Environmental Policy Act (NEPA). Additionally, the court determined that Fasken’s late-filed contentions were procedurally defective, untimely, and immaterial.The court denied all the petitions for review, affirming the NRC’s decisions to deny the requests for intervention. View "Beyond Nuclear, Inc. v. NRC" on Justia Law