Justia U.S. D.C. Circuit Court of Appeals Opinion Summaries

Articles Posted in Energy, Oil & Gas Law
by
For seven years, NTE worked to build a natural gas-fueled power plant in Killingly, Connecticut to sell electricity on the New England grid. NTE worked with ISO, the independent system operator authorized by the Federal Energy Regulatory Commission (FERC) to manage the regional grid, to have the project “qualified” to bid for the right to sell electricity. NTE secured a “capacity supply obligation” (CSO) for the 2022 commitment period. NTE secured a guaranteed income stream for the first seven years of the plant’s operation.NTE subsequently encountered setbacks that prevented it from meeting its financing and construction goals. On November 4, 2021, NTE told ISO that it remained confident it could complete construction on time but ISO-NE asked FERC to terminate the Killingly plant’s CSO. In January 2022, FERC did so. In February, the Second Circuit issued an emergency stay of FERC’s order. FERC likely fell short of its obligation under the Administrative Procedure Act to explain its decision. Absent emergency relief, FERC’s order would have irreparably harmed NTE, preventing it from participating in an auction to sell future electricity capacity to New England consumers. Nothing in FERC’s reasoning suggests the risk that incumbents may have to reallocate electricity capacity amongst themselves outweighs the harm of delaying NTE’s project, which could benefit consumers through more efficient, less expensive electricity. View "In re: NTE Connecticut, LLC" on Justia Law

by
The owners of New England electric generation facilities are paid through formula rates established by ISO New England’s (a regional transmission organization) open access transmission tariff. The owners challenged Federal Energy Regulatory Commission’s (FERC) orders approving Schedule 17, an amendment to the ISO tariff, establishing a new recovery mechanism for costs incurred by certain electric generation and transmission facilities to comply with mandatory reliability standards FERC had approved.FERC ruled that the owners could use Schedule 17 to recover only costs incurred after they filed and FERC approved a cost-based rate under the Federal Power Act (FPA), 16 U.S.C. 824d. FERC reasoned that recovery was limited to prospective costs, citing the filed rate doctrine, which forbids utilities from charging rates other than those properly filed with FERC, and its corollary, the rule against retroactive rate-making, which prohibits FERC from adjusting current rates to make up for a utility’s over- or under-collection in prior periods.The D.C. Circuit denied the petition for review. FERC’s application of the filed rate doctrine and the rule against retroactive rate-making to Schedule 17 was not arbitrary or capricious. Schedule 17 does not expressly permit recovery of mandatory reliability costs incurred prior to a facility’s individual FPA filing. View "Cogentrix Energy Power Management, LLC v. Federal Energy Regulatory Commission" on Justia Law

by
The San Francisco Public Utilities Commission owns a power supply system in the Hetch Hetchy Valley and transmission lines but does not own distribution lines and relies on PG&E’s distribution system. The Commission is both a customer and a competitor of PG&E. The Federal Energy Regulatory Commission (FERC) approved PG&E’s Tariff, which stated the generally applicable terms for “open-access” wholesale distribution service. In 2019, San Francisco filed a complaint under the Federal Power Act (FPA), 16 U.S.C. 824e, 825e, 825h, challenging PG&E’s refusal to offer secondary-voltage service in lieu of more burdensome primary-voltage service to certain San Francisco sites and provide service to delivery points that San Francisco maintains are eligible for service under the Tariff’s grandfathering provision. PG&E maintained that it had not given customers the right to dictate the level of service to be received and that any denials of secondary-voltage service were supported by “technical, safety, reliability, and operational reasons.”FERC denied San Francisco’s complaint, ruling that PG&E should retain discretion to determine what level of service is most appropriate for a customer because the provider “is ultimately responsible for the safety and reliability of its distribution system.” The D.C. Circuit vacated and remanded, citing FERC’s own precedent and noting a “troubling pattern of inattentiveness to potential anticompetitive effects of PG&E’s administration of its open-access Tariff.” View "City and County of San Francisco v. Federal Energy Regulatory Commission" on Justia Law

by
Duke generates electricity for Power, a “joint agency” of 32 North Carolina municipalities. Power pays Duke an Energy Charge that “reimburses Duke only for its fuel costs and variable operations and maintenance costs associated with producing the energy consumed by Power" and a Capacity Charge, designed to cover Duke’s fixed costs and provide a return on its infrastructure investments, calculated by determining its pro-rata share of the demand on Duke’s system during a one-hour “snapshot” of system usage taken during the peak hour on Duke’s system each month.Their agreement regulates activities Power may employ to modify its electricity use, including Demand-Side Management and Demand Response. Demand-Side Management involves end-users accepting an inducement to sign up for a program where Power can turn off and on their appliances around high-demand periods. Demand Response involves a supplier providing end-users information on the price of energy at a given time and those end users then modifying their consumption to avoid elevated prices.In 2019, Power petitioned the Federal Energy Regulatory Commission (FERC) arguing that the provisions that permit Demand-Side Management and Demand Response activities permit deploying battery storage technology to reduce metered demand during peak load periods and drawing from those batteries during the high-demand “snapshot” hour. Concerned that Power would reduce its Capacity Charge to zero, Duke opposed the petition. The D.C. Circuit affirmed FERC’s grant of Power’s petition, finding that the agreement permits Power to use battery storage technology as either Demand-Side Management or Demand Response. View "Duke Energy Progress, LLC v. Federal Energy Regulatory Commission" on Justia Law

by
The DC Circuit granted the City's petitions for review of FERC orders rejecting the City's complaint regarding periodic outflow coming from the operation of the Pensacola Project, a downstream dam licensed by FERC. The court found FERC's position unpersuasive and remanded for the Commission to determine the role of the Corps, the responsibility the Authority bears if it caused flooding in the City, analyze the evidence petitioner has produced, and finally interpret the Pensacola Act. View "The City of Miami, Oklahoma v. Federal Energy Regulatory Commission" on Justia Law

by
Several utilities that are managed by the Southwest Power Pool (SPP), a regional transmission operator, paid for upgrades to the transmission grid. The operative tariff required other utilities who benefitted from these upgrades to share the costs of the expanded network. The tariff, however, also required SPP to invoice the charges monthly and to make adjustments within one year. The reimbursement calculation proved complicated. It took SPP eight years to implement it, during which time SPP did not invoice for the upgrade charges. FERC initially granted SPP a waiver of the tariff’s one-year time bar but later determined it lacked the authority to waive this provision retroactively. FERC’s revised determination meant the utilities that had made substantial outlays for upgrades were denied reimbursement for the eight years that had elapsed.The D.C. Circuit denied petitions for review filed by SPP and a company that sponsored upgrades and has been denied reimbursement. Once a tariff is filed, FERC has no statutory authority (16 U.S.C. 824d(d)) to provide equitable exceptions or retroactive modifications to the tariff. SPP may impose only those charges contained in the filed rate. Because the one-year time bar for billing is part of the filed rate, FERC could not retroactively waive it, even to remedy a windfall for users of the upgraded networks. View "Oklahoma Gas and Electric Co. v. Federal Energy Regulatory Commission" on Justia Law

by
Entergy, a public utility holding company, owns five operating companies that sell electricity in four states, including Louisiana. The companies have been governed by an agreement requiring them to act as a “single economic unit” and requiring “rough equalization” of their production costs. In 2005, the Federal Energy Regulatory Commission (FERC) determined that the production costs were not roughly equal and imposed a “bandwidth remedy”: Whenever the yearly production costs of an individual operating company deviated from the average by more than 11%, companies with lower costs were required to pay companies with higher costs as necessary to bring all five companies within that range. Entergy filed a tariff establishing a formula to calculate production costs subject to the bandwidth remedy, which FERC largely accepted.Utilities often spread their recovery of large, non-recurring costs by creating a regulatory asset, a type of credit. The company then amortizes the asset in later years, creating debits chargeable to customers. Historically, the Entergy companies recorded regulatory assets and their related amortization expenses in FERC accounts not referenced in the bandwidth formula; this effectively accounted for deferred production costs when they were incurred, rather than when the related amortization expenses were recorded. FERC rejected that approach and excluded purchased-power costs that a Louisiana affiliate incurred in 2005 and amortized in 2008 and 2009.The D.C. Circuit denied the Louisiana Public Service Commission’s petition for review. The Federal Power Act requires electric utilities to charge “just and reasonable” rates. 16 U.S.C. 824d(a). If FERC finds a rate unreasonable, it may establish a just and reasonable rate; FERC may reallocate production costs under the Entergy system agreement, including by ensuring compliance with the bandwidth remedy. View "Louisiana Public Service Commission v. Federal Energy Regulatory Commission" on Justia Law

by
A 2015 auction for electrical capacity (commitments by power plants to provide electricity to utilities in the future) in Illinois produced a striking result. Capacity in neighboring regions uniformly sold for less than $3.50 per megawatt-day; in a region covering much of Illinois, the auction resulted in capacity prices of $150 per megawatt-day, a nearly ninefold increase from the prior year’s price of $16.75. The Federal Energy Regulatory Commission identified numerous problems with the existing auction rules and ordered that the rules be changed prospectively. FERC also launched an investigation into potential market manipulation in the 2015 Auction but later ruled that the identified flaws in the auction rules and the high price range those rules established, plus the allegations of market manipulation, did not call into question the 2015 Auction or the price it produced.The D.C. Circuit granted a petition for review in part. Under the Federal Power Act, 16 U.S.C. 791, FERC need not approve every auction price before it goes into effect. That is not what the market-based rate scheme requires. However, FERC’s analysis of the 2015 Auction, was arbitrary and capricious; it failed to adequately explain why the problems it identified in the existing auction rules affecting pricing— problems it ordered fixed going forward—did not also affect the fairness of the 2015 Auction. View "Public Citizen, Inc. v. Federal Energy Regulatory Commission" on Justia Law

by
The Federal Energy Regulatory Commission authorized the construction and operation of three liquified natural gas (LNG) export terminals on the shores of the Brownsville Shipping Channel in Cameron County, Texas, and the construction and operation of two 135-mile pipelines that will carry LNG to one of those terminals. Objectors filed challenges under the National Environmental Policy Act (NEPA), 42 U.S.C. 4332(2)(C); the Administrative Procedure Act (APA), and the Natural Gas Act (NGA), 15 U.S.C. 717b(a).The D.C. Circuit dismissed the petition concerning the Annova Terminal as moot, and granted the petitions with respect to the Rio Grande and Texas Terminals, without vacatur. The Commission’s analyses of the projects’ impacts on climate change and environmental justice communities were deficient under NEPA and the APA, and the Commission failed to justify its determinations of public interest and convenience under Sections 3 and 7 of the NGA. On remand, the Commission must explain whether 40 C.F.R. 1502.21(c) requires it to apply the social cost of carbon protocol or some other analytical framework, as “generally accepted in the scientific community” within the meaning of the regulation, and if not, why not. View "Vecinos para el Bienestar de la Comunidad Costera v. Federal Energy Regulatory Commission" on Justia Law

by
The Clean Air Act’s Renewable Fuel Standard Program (42 U.S.C. 7547(o)(2)(A)(i)) calls for annual increases in the amount of renewable fuel introduced into the U.S. fuel supply and sets annual targets for renewable fuel volumes. Each year, EPA implements those targets but has certain waiver authorities to reduce the annual targets below the statutory levels. Companies that produce renewable fuels argued that EPA’s 2019 volume levels (83 Fed. Reg. 63,704) were too low; fuel refiners and retailers argued that the 2019 volumes were too high. Environmental organizations challenged various aspects of the 2019 Rule relating to environmental considerations.The D.C. Circuit denied their petitions for review except for the environmental organizations’ challenges concerning whether the 2019 Rule would affect listed species, which it remanded without vacatur. The court upheld EPA’s 2019 continuation of its practice of granting exemptions to small refineries after promulgating the annual percentage standards; EPA’s decision to exclude electricity generated from renewable biomass (a form of cellulosic biofuel) from its cellulosic biofuel projection in the 2019 Rule; EPA’s determination that the 2019 volumes would not cause severe economic harm; and EPA’s decision not to obligate ethanol blenders under the RFS Program. EPA adequately explained its refusal to exercise the inadequate domestic supply waiver. EPA did not act arbitrarily in estimating that 100 million gallons of sugarcane ethanol were “reasonably attainable” for 2019. View "Growth Energy v. Environmental Protection Agency" on Justia Law