Justia U.S. D.C. Circuit Court of Appeals Opinion Summaries
Articles Posted in Utilities Law
Basin Electric Power Cooperative v. FERC
Basin Electric Power Cooperative is a not-for-profit, member-owned electric cooperative that sells wholesale electricity to its member systems, including Tri-State Generation and Transmission Association. Tri-State, in turn, provides power to its own members such as Northwest Rural Public Power District, which distributes electricity in Nebraska and accounts for a notable share of Tri-State’s Eastern Interconnection energy demands. Two contracts govern the parties’ relationships: one between Basin and Tri-State (the Basin/Tri-State Agreement) and another between Tri-State and Northwest Rural. In 2022, Northwest Rural notified Tri-State of its intent to withdraw from membership and terminate its agreement, prompting Basin to argue that such a withdrawal would breach its contract with Tri-State.Initially, Basin sought relief in the United States District Court for the District of North Dakota, but the court dismissed the case, deferring to the Federal Energy Regulatory Commission (FERC) for primary jurisdiction. After further proceedings, FERC considered a complaint by Northwest Rural seeking confirmation that its withdrawal was permissible under the Basin/Tri-State Agreement. FERC found that the contract expressly contemplated such member withdrawals and provided a mechanism for Tri-State and Basin to address the implications, holding that Northwest Rural’s withdrawal would not constitute a breach by Tri-State. Basin’s subsequent motions for rehearing were denied, and it filed petitions for review.The United States Court of Appeals for the District of Columbia Circuit reviewed the FERC orders. The court held that Section 9 of the Basin/Tri-State Agreement unambiguously permits Tri-State to transfer assets—such as allowing a member to withdraw—without Basin’s approval, provided certain conditions are met. The court found FERC’s interpretation neither arbitrary nor capricious and denied Basin’s petitions for review, affirming that Northwest Rural’s withdrawal does not breach the Basin/Tri-State Agreement. View "Basin Electric Power Cooperative v. FERC" on Justia Law
Posted in:
Contracts, Utilities Law
People of the State of Michigan v. DOE
Consumers Energy Company, a private utility in Michigan, planned to retire the J.H. Campbell Generating Plant, a decades-old coal facility, and replace it with newer, cleaner, and more reliable energy sources. The proposed closure and replacement plan underwent extensive review by the Michigan Public Service Commission and the Midcontinent Independent System Operator (MISO), both of which ultimately approved it after finding that the substitute resources would meet reliability standards and improve affordability and environmental outcomes. As the retirement date neared, the Department of Energy (DOE) issued an order under section 202(c) of the Federal Power Act, compelling Consumers Energy to keep the Campbell plant operational, citing an energy emergency in the region.The Michigan Public Service Commission approved the integrated resource plan after a contested case proceeding, finding that it would enhance resource adequacy. The Michigan Court of Appeals affirmed this decision, concluding that substantial evidence supported the Commission’s approval. MISO also determined that Campbell’s retirement, as planned, would not threaten reliability. Consumers Energy documented sufficient capacity to meet projected demand, and MISO’s resource auction confirmed adequate supply and reserve margins for the relevant period. No state or regional entity requested FERC intervention, nor did the Michigan governor declare an energy emergency.The United States Court of Appeals for the District of Columbia Circuit reviewed the DOE’s order. The court held that section 202(c) grants DOE limited, emergency authority to intervene only when an electricity shortage creates an acute risk that cannot be timely addressed by state or regional planning, and immediate federal action is necessary. The court found that DOE’s asserted circumstances did not constitute such an emergency, as reasonable alternatives existed and the state had adequately planned for resource adequacy. Accordingly, the court granted the petitions for review and vacated DOE’s order. View "People of the State of Michigan v. DOE" on Justia Law
Posted in:
Government & Administrative Law, Utilities Law
Midcontinent Independent System Operator Transmission Owners v. FERC
A group of electric transmission companies operating within the Midcontinent Independent System Operator (MISO) region, along with the Louisiana Public Service Commission (LPSC), challenged actions taken by the Federal Energy Regulatory Commission (FERC) regarding the rates charged to electricity customers. The dispute centered on the return-on-equity (Return) component of transmission rates, which compensates transmission owners for their investments. In 2013 and 2015, customers filed two complaints with FERC alleging that the Return was unlawfully high and violated the Federal Power Act's mandate for "just and reasonable" rates. FERC responded with a series of orders adjusting the Return and ordering limited refunds, but its methodology was challenged and ultimately vacated by the United States Court of Appeals for the District of Columbia Circuit in MISO Transmission Owners v. FERC, which remanded the matter for further proceedings.On remand, FERC issued new orders revising the Return, requiring Transmission Owners to provide refunds for the statutorily authorized 15-month period and, in light of the prior vacatur, ordering additional refunds from September 28, 2016 through October 17, 2024. FERC dismissed the second customer complaint after finding the revised Return was just and reasonable and declined to order additional refunds. Both Transmission Owners and LPSC sought rehearing, raising further objections to the refund periods and the methodology used to set the Return.The United States Court of Appeals for the District of Columbia Circuit reviewed the petitions. The court held that FERC acted within its authority in backdating refunds to align with the judicial vacatur, pursuant to FERC’s remedial powers under section 309 of the Federal Power Act. The court also found Transmission Owners lacked standing to challenge FERC’s consideration of the second complaint. LPSC’s objections to FERC’s methodology were rejected under the law-of-the-case doctrine and as lacking merit. The court denied in part and dismissed in part Transmission Owners’ petitions, and denied LPSC’s petitions for review. View "Midcontinent Independent System Operator Transmission Owners v. FERC" on Justia Law
Posted in:
Utilities Law
Maryland Office of People’s Counsel v. FERC
PJM Interconnection, LLC, which manages electricity transmission across several Mid-Atlantic and Midwestern states, conducted its 2024/2025 capacity auction based on certain published parameters intended to ensure sufficient capacity for future electricity needs. After bidding closed, PJM discovered an error in the Locational Delivery Area Reliability Requirement for the Delmarva Power & Light Company South Zone, which would result in inflated auction prices and excess capacity charges for consumers. PJM sought to amend its tariff to correct this issue before finalizing the auction results, and the Federal Energy Regulatory Commission (FERC) approved PJM's request.Capacity suppliers challenged FERC’s approval in the United States Court of Appeals for the Third Circuit, which vacated the decision, finding that the amendment was retroactive and violated the filed-rate doctrine. FERC, complying with the Third Circuit’s mandate, directed PJM to proceed with the unamended tariff, resulting in higher costs for consumers. Following this, agencies, customers, and entities representing customers’ interests filed a complaint under section 206 of the Federal Power Act, seeking modification of the auction outcome. FERC denied the complaint, stating that the Third Circuit’s ruling foreclosed any relief.The United States Court of Appeals for the District of Columbia Circuit reviewed FERC’s orders. The court held that FERC’s denial of the complaint was legally erroneous because the Third Circuit’s decision did not address whether FERC could use its section 206 authority to modify the auction result. The D.C. Circuit clarified that section 206(b) of the Federal Power Act provides a statutory exception to the general prohibition on retroactive rate changes. The court granted the petition for review, vacated FERC’s orders denying the complaint, and remanded the case to FERC for further proceedings. View "Maryland Office of People's Counsel v. FERC" on Justia Law
Posted in:
Government & Administrative Law, Utilities Law
Capital Power Corp. v. Federal Energy Regulatory Commission
Several electricity generators challenged a change in how they are compensated for producing reactive power, a component of electricity necessary for grid stability but not directly consumed by end users. For many years, the Midcontinent Independent System Operator (MISO) provided generators with cost-based compensation for reactive power, in addition to market-based payments for real power. In 2022, MISO amended its tariff to eliminate separate compensation for reactive power, meaning neither transmission owners nor independent generators would receive payment for producing it within a standard range. This change was approved by the Federal Energy Regulatory Commission (FERC) and given immediate effect, despite objections from generators who argued they had made investments and entered contracts in reliance on the prior compensation structure.FERC approved MISO’s tariff amendment and denied requests for rehearing, concluding that the comparability standard justified the change and that generators’ reliance interests were either unsupported or outweighed by other considerations. FERC reasoned that generators should not have expected compensation for reactive power to continue indefinitely, especially since prior orders had made such compensation contingent on similar treatment for transmission owners. Generators petitioned the United States Court of Appeals for the District of Columbia Circuit for review, arguing that FERC failed to adequately consider their short-term financial reliance on the previous compensation scheme.The United States Court of Appeals for the District of Columbia Circuit held that FERC acted arbitrarily and capriciously by failing to adequately consider the generators’ short-term reliance interests before allowing the tariff change to take immediate effect. The court did not address the substantive validity of the tariff amendment itself but found that FERC’s explanation was insufficient regarding the abrupt elimination of compensation. The court granted the petitions for review, set aside FERC’s orders, and remanded the matter for further proceedings. View "Capital Power Corp. v. Federal Energy Regulatory Commission" on Justia Law
Posted in:
Government & Administrative Law, Utilities Law
Louisville Gas and Electric Company v. Federal Energy Regulatory Commission
Two electric utility companies merged in 1998, with federal approval conditioned on their participation in a regional grid operator to prevent customers from paying multiple, overlapping transmission fees (“pancaked” rates). Several years later, the merged company was allowed to leave the grid operator, but only if it continued to protect certain customers from redundant fees through a special rate schedule. In 2019, the company sought to end this obligation, arguing that continued protection was no longer necessary. The Federal Energy Regulatory Commission (FERC) granted this request, but the United States Court of Appeals for the District of Columbia Circuit vacated that order, finding FERC had failed to consider the impact on customer rates.On remand, FERC issued a new order denying the company’s request to end the fee protection, concluding that removing the protection would adversely affect rates for certain customers and that the benefits of removal did not outweigh these harms. FERC also denied rehearing, maintaining that the company had not shown sufficient alternative protections for affected customers. The company then petitioned the United States Court of Appeals for the District of Columbia Circuit for review, arguing that FERC’s orders were arbitrary, capricious, and inconsistent with law and precedent.The United States Court of Appeals for the District of Columbia Circuit held that FERC did not violate its statutory mandate or precedent in its general approach. However, the court found that FERC failed to adequately consider whether alternative customer protections, such as transition agreements, could mitigate the adverse rate impacts. The court therefore granted the petitions for review, vacated FERC’s orders, and remanded the matter for further consideration of whether such protections would suffice to offset the adverse effects on rates. View "Louisville Gas and Electric Company v. Federal Energy Regulatory Commission" on Justia Law
Posted in:
Utilities Law
Central Hudson Gas & Electric Corporation v. FERC
Petitioners, who own New York’s electric-transmission grid, sought to finance upgrades required when new power sources connect to the grid. This would allow them to raise rates and earn a return on these investments. However, the Federal Energy Regulatory Commission (FERC) denied their requests to change the rules prohibiting owner upgrade funding.The transmission owners filed two petitions with FERC on April 9, 2021, under Sections 205 and 206 of the Federal Power Act, requesting amendments to the Open Access Transmission Tariff (OATT) to allow them to fund interconnection upgrades. On September 3, 2021, FERC rejected the Section 205 filing, stating that the owners’ agreement with the New York Independent System Operator (NYISO) limited their Section 205 rights. FERC also dismissed the Section 206 complaint, concluding that the owners failed to demonstrate that the existing funding mechanism was unjust, unreasonable, unduly discriminatory, or preferential. The owners’ requests for rehearing were deemed denied by operation of law on November 4, 2021, and FERC issued a new order on March 24, 2022, modifying its original orders.The United States Court of Appeals for the District of Columbia Circuit reviewed the case and upheld FERC’s decisions. The court found that FERC acted reasonably in dismissing the Section 205 filing, as the owners had relinquished their rights to file for changes to the OATT without NYISO’s approval. The court also agreed with FERC’s dismissal of the Section 206 complaint, noting that the owners failed to provide sufficient evidence that the current rates were unjust or unreasonable. The court concluded that FERC’s orders were not arbitrary or capricious and denied the owners’ petitions for review. View "Central Hudson Gas & Electric Corporation v. FERC" on Justia Law
Posted in:
Government & Administrative Law, Utilities Law
Aenergy, S.A. v. Republic of Angola
Aenergy, S.A. (Aenergy) sought damages from the Republic of Angola for unpaid work related to power turbines to be installed in Angola. Aenergy had previously entered into contracts with Angolan utility subsidiaries to construct, supply, and maintain power plants and water infrastructure. The contracts involved General Electric (GE) turbines and were financed by a credit line from GE Capital. Aenergy alleged that a GE accounting error led to forged contract amendments, resulting in the Angolan government terminating the contracts and seizing turbines.Aenergy initially filed a lawsuit in the U.S. District Court for the Southern District of New York (SDNY), which dismissed the case on forum non conveniens grounds. The court found that Angola was an adequate alternative forum for the dispute. The Second Circuit affirmed this decision, emphasizing that Aenergy could bring similar claims in Angola, even if the breach-of-contract claim was time-barred. Aenergy's requests for rehearing and certiorari were denied.Aenergy then filed a new lawsuit in the U.S. District Court for the District of Columbia, focusing on breach of contract for unpaid work. The district court dismissed the case, citing issue preclusion based on the prior SDNY and Second Circuit rulings. The court also conducted a fresh forum non conveniens analysis, concluding that Angola remained the appropriate forum.The United States Court of Appeals for the District of Columbia Circuit reviewed the case and affirmed the district court's dismissal. The court held that issue preclusion applied because the adequacy of Angola as an alternative forum had already been determined in the previous litigation. The court found that Aenergy's trimmed-down complaint did not change the forum non conveniens analysis, and the Supreme Court of Angola's subsequent dismissal of Aenergy's administrative action did not alter the adequacy of Angola as a forum. View "Aenergy, S.A. v. Republic of Angola" on Justia Law
Entergy Arkansas, LLC v. FERC
In February 2021, a severe cold snap hit the central United States, causing widespread power outages and fatalities. This event highlighted the need for improved grid reliability. The Midcontinent Independent System Operator (MISO), which manages the electrical grid in the region, proposed changes to its capacity market to address these issues. MISO's new system includes seasonal capacity markets, a revised method for calculating generator capacity, and new rules for generator outages. The Federal Energy Regulatory Commission (FERC) approved these changes.Entergy Arkansas, LLC, along with other companies, petitioned for review of FERC's approval, arguing that FERC acted arbitrarily and capriciously. Entergy challenged three main aspects: the new method for calculating generator capacity, the requirement for generator owners to replace capacity if offline for more than 31 days in a season, and the 120-day notice requirement for planned outages. Entergy was supported by several intervenors, including public utilities commissions and the East Texas Electric Cooperative.The United States Court of Appeals for the District of Columbia Circuit reviewed the case. The court found that FERC had adequately explained its approval of MISO's changes. FERC's reliance on a study showing the new methodology's accuracy was deemed reasonable. The court also upheld the 31-day capacity replacement rule and the 120-day notice requirement, finding that FERC had provided sufficient rationale for these rules. The court denied Entergy's petitions for review and did not address issues raised solely by the intervenors. The court concluded that FERC's decisions were not arbitrary or capricious and were supported by substantial evidence. View "Entergy Arkansas, LLC v. FERC" on Justia Law
Posted in:
Government & Administrative Law, Utilities Law
Shell Energy North America (US), L.P. v. Federal Energy Regulatory Commission
This case involves the sale of electricity under the Federal Power Act and the Federal Energy Regulatory Commission's (FERC) efforts to limit the rates at which certain wholesale electricity is traded. For over two decades, FERC has maintained a "soft" price cap for certain short-term electricity sales in parts of the western United States. In August 2020, a heat wave in the western United States led to increased prices in the market for short-term electricity supply. Some of the short-term sales occurred at prices above FERC's soft cap. Sellers who transacted at above-cap prices were required to justify those transactions to FERC or be required to refund sale prices that exceed the cap. After reviewing the sellers' justification filings, FERC determined that some sellers had failed to justify their above-cap sales and ordered partial refunds.The case was brought before the United States Court of Appeals for the District of Columbia Circuit. The court found that FERC should have conducted a Mobile-Sierra analysis, which presumes that contract rates formed through arms-length, bilateral negotiation are reasonable, before ordering refunds. The court agreed with the sellers that FERC erred by failing to conduct this analysis prior to ordering refunds. As a result, the court granted the sellers' petitions for review, vacated the orders they challenged, and remanded for further proceedings. The court dismissed the consumers' petitions for review as moot. View "Shell Energy North America (US), L.P. v. Federal Energy Regulatory Commission" on Justia Law
Posted in:
Energy, Oil & Gas Law, Utilities Law